Fast, Reliable Measurements
Give Us An Effective Way of Planning Preventive Maintenance
In Advance
SPM
Instrument
"This equipment has given us completely new opportunities
to plan maintenance activities in advance. This has meant
that we've been able to minimise the number of breakdowns,
thus increasing our profits."
Olle Regnell is a preventive maintenance technician at the
Skoghall Mill, a company within the StoraEnso group. In 1993,
the company installed extensive on-line equipment for the shock
pulse measuring of bearings on Board Machine No. 7 (BM 7).
Thanks to this investment, today they can measure,with a focus
on wrapping, drying and pressing quantities in the board machine,
1,050 items of stock every 24 hours. Earlier it took between
four and six weeks to do the same job!" Being able to measure
quickly and accurately has meant that we can see rising trends
and plan things so that replacements can be introduced during
scheduled interruptions," says Olle Regnell.
"Being able to measure quickly and accurately has meant that
we can see rising trends and plan things so that replacements
can be introduced during scheduled interruptions," says Olle
Regnell, preventive maintenance technician.
"After installation of the SPM system, breakdowns have been
very rare, which has made it possible to avoid production losses
worth millions."
Millions of Swedish crowns
What effect has being able to reduce the number of breakdowns
had on the company economically? "It's always difficult to
say to the penny how much we could have saved if we are able
to act before a breakdown happens. But we are really talking
about major amounts and the measuring system has more than
paid for itself several times over."
A look in the rear-view mirror tells us that before 1993,
the mill suffered three or four breakdowns, caused by stock
damage, every year. After installation of the SPM system, breakdowns
have been very rare, which has made it possible to avoid production
losses worth millions.
A guide roll bearing takes five or six hours to replace and
if we multiply that by 150,000 Swedish crowns an hour, which
is what the Skoghall Mill loses in revenue when BM 7 is idle,
we arrive at "major sums", as Olle puts it.
Down to 100 hours!
In addition to this investment, which is reducing what is
traditionally regarded as pure maintenance costs, it has also
opened the door to more efficient use of capital. "We don't
have to keep as many spare parts in stock. In fact, we can
even allow our suppliers to take over some storage of stocks," says
Göran Regnell, Manager of Technique, a unit whose 360 employees
work with plant and IT, as well as maintenance.
"It's important that those of us who work with maintenance
are able to present our opinions early in the design and purchasing
phases," says Göran Regnell. Indicating that studies showing
that some 60 per cent of the incidents that have caused breakdowns
were directly related to design and purchasing.
The reduction in the number of breakdowns has made it possible
for the company to reduce the number of unscheduled interruptions
at BM 7, from 250 to 150-200 hours per year, a level that has
held over the past four years. "We've switched from corrective
to preventive maintenance and got good results. Now we're aiming
to press that figure down to 100 hours," says Göran Regnell.
Integrating operational reliability
To arrive at that goal, the company is consciously working
to integrate operational reliability into the production organisation. "Our
maintenance organisation is set up to support the main process.
Thus it makes sense for us to be located close to each other.
It is also important that those of us who work with maintenance
get to present our opinions already in the design and purchasing
phases," says Göran Regnell, indicating studies showing that
some 60 per cent of the incidents that have caused breakdowns
were directly related to design and purchasing.
Raising the ceiling on OEE
When production is under way, it's up to the maintenance
organisation to raise the OEE, Overall Equipment Efficiency,
in other words, to exploit the mill to the maximum.
The OEE model has been in use at the Skoghall Mill since
the mid-'90s, and losses in time, speed and quality have been
reduced by taking various measures. "Committed, knowledgeable
staff and RAPS, a system for maintenance, are two important
reasons for us coming a good distance along the way," says
Göran Regnell.
Nowadays, staff aren't just planning and carrying out maintenance
assignments. They register the fault itself, when it occurred,
what type of fault it is, what measures have been taken and
how long it took, etc. Over 90 per cent of employees' time
is reported in RAPS. "At first, a lot of people thought registration
was just bureaucracy, but today they accept it wholeheartedly.
The reason for this that they can see how much of an advantage
registration gives them when they're planning forthcoming assignments," says
Göran Regnell.
"We can see rising trends and plan things so that replacements
can be introduced during scheduled interruptions"
The group has the right competence
The records stored in RAPS also give the Skoghall Mill very
good input data for use in evaluating and analysing maintenance
measures, and for carrying out improvements."Thanks to the
information RAPS gives us, we can concentrate our efforts on
the problems that cause the greatest financial losses. We can
even see exactly what types of competence are needed in the
different improvement groups that we put together to find solutions
to maintenance-related problems," says Göran Regnell.
"This effective SPM measuring equipment is also easy to use," says
Lennart Wallenius, preventive maintenance technician at Stora
Enso. |