Electrical Troubleshooting
From Plant Maintenance Resource Center
Posted 8-23-04
A laptop computer with PLC programming, communication, and
operating programs is a necessary tool in today’s modern
plant. Engineers, production supervisors, maintenance supervisors,
maintenance technicians, electricians, instrument technicians,
and maintenance mechanics all need to have PLC and computer
knowledge, training and skills in troubleshooting.
On the job training on PLC’s is usually not very effective
until the person being trained has reached a certain level
of expertise in several areas. Knowledge and skills in electricity,
troubleshooting, and computer operation are necessary prerequisites
to effectively assimilate basic PLC training. The author found
that long term retention of material studied was higher from
a vocational course taken at a local junior college than from
a fast-paced, cram-course through a manufacturer.
The manufacturer’s course covered essentially the same
material as a course at the junior college (JC). The major
differences were the amount of study time and shop time. The
JC course was four hours of class time per week for 15 weeks.
There were three hours of shop time doing actual hands on work
of the problems and material covered in the first hour. Additional
time was spent at home studying the manual and writing programs.
Also, the JC was open at night for extra shop time on the PLC’s
and computers.
In contrast, the manufacturer’s course was five, eight
hour days. Class work was extremely fast and condensed in order
to cover the amount of material involved. The instructor was
very knowledgeable and covered the course material as we tried
to input the programs into desktop training equipment in order
to see how it worked. By the end of each day, our minds were
jammed with information. By the end of the week, we all passed
the course, but I had a hard time remembering what we had studied
on the first day.
Basic troubleshooting techniques apply to every situation
and occupation. Positive identification of the problem(s) is
absolutely essential to solving the problem(s). Many times,
the inexperienced troubleshooter will mistake one or more of
the symptoms for the problem(s). Solving the symptom(s) will
normally just postpone the problem(s) to a later date. By which
time, the problem(s) may have grown to mountainous proportions.
An example is when a person experiences a headache and takes
a mild pain reliever, such as aspirin. The actual problem might
be any number of things: eyes need to be checked, medication
or lack of medication, muscle strain, stress, tumor, blood
vessel blockage, or old war injury. The same thing occurs in
industry, a fuse in a circuit blows and the maintenance person
gets the replacement fuse and inserts it into the fuseholder.
There are many things that could have caused the fuse to blow,
depending on the complexity of the circuit.
Excess current caused the fuse to open (blow). Excess current
could have been caused by: overload on the load; short circuit
between the wires, grounded wires, short circuit in the load,
ground in the load, voltage spike, voltage droop, etc. If the
maintenance person does not troubleshoot the circuit prior
to replacing the fuse and restoring power, negative consequences
could arise.
It is not uncommon for a process to develop a number of small
problems and continue to function at a degraded level of operational
capability. Then, one more small problem occurs and the whole
process breaks down. Finding and correcting the last problem
will not necessarily restore the operational capability of
the process. The process continued operations with the small
problems, but the small problems may not allow the process
to restart from a dead stop. All the other small problems must
be identified and corrected before the process is restored
to full operational capability.
This situation arises in industry as well as a person. The
person can continue to function with a number of small problems,
such as fatigue, blood pressure problems, hardening of the
arteries, artery blockage, but one more small blood clot in
the wrong place could easily cause the death of the person.
Clearing the blood clot does no good to the person. They will
not be restored to full operational capability.
Troubleshooting In The Field
Unless prior experience dictates otherwise, always begin at
the beginning.
Ask questions of the Operator of the faulty equipment:
- Was equipment running when problem occurred?
- Does the Operator know what caused the problem, and if
so, what, in their opinion, caused the problem?
- Is the equipment out of sequence?
- check to ensure there is power
- turn
on circuit breaker, ensure motor disconnect switch is on,
and operate start button/switch
Use voltmeter to check the following at incoming
and load side of circuit breaker(s) and/or
fuses, ensure
that voltages are
normal on all legs and read voltage to ground
from each leg:
- main power, usually 460 VAC between phases and 272 to ground
- control & power, 208/240 between phases and 120 to
ground and 120 VAC to neutral on a grounded system
- low voltage control power, usually 24
to 30 VAC and/or VDC between phases
and possibly to ground, usually
negative is
connected to ground
Check controlling sensors in area of
problem, then make complete check of
all sensors, limit switches and other
switches to
ensure they are in correct position, have power, are programmed,
set, and are functioning correctly. If and when a problem is found, whether electrical or mechanical,
the problem should be corrected and the fault-finding begun
anew, a seemingly unrelated fault or defect could be the cause
of the problem.
When there is more than one fault, the troubleshooting is
exponentially more difficult, do not assume that all problems
are solved after completing one, always test the circuit and
operation prior to returning the equipment to service.
If available, check wiring diagrams and PLC programs to isolate
problem.
Variable Frequency Drive (VFD) can be reset by turning power
off, wait till screen is blank and restore power; on some VFD’s,
press Stop/Reset – then press Start.
Check that wiring is complete and that wires and connections
are tight with no copper strands crossing from one terminal
to another or to ground.
Ensure that the neutral reading is good and that the neutral
is complete and not open.
Motor Testing In Shop
Prior to connecting a motor:
- move motor to electric shop motor test and repair station
- connect motor leads for 460 volt operation and wrap connections
with black electrical tape
- check motor windings with an ohmmeter, each reading between
phases should be within one or two ohms of each other;
A to B, B to C, A to C
- use megohmmeter to check insulation resistance to ground
of motor windings on 500 volt scale; minimum reading
is 1000 ohms
of resistance per volt of incoming power that motor
will be connected to
- connect motor to power test leads and safety ground after
checking that test lead power is shut off; secure
motor to table to
prevent motor from jumping when started; turn disconnect
on; press start button; check “T” leads
for motor amperage; check for abnormal sounds and
heat in bearings or windings;
clean motor shaft; shut down and disconnect
Motor Testing In Field
When a motor overload or circuit breaker trips and/or
blows fuses, certain procedures and tests should
be carried out:
- lockout and tagout main circuit breaker;
- test insulation resistance of motor wires and windings
by using megohmmeter between T1, T2, & T3 leads and
ground, then;
- test “T” leads to motor with ohmmeter for continuity
and ohmage of windings between A to B, B to C, A to C; each
resistance should be within 1 or 2 ohms of each other; if the
ohms readings are significantly different, or, if there is
no continuity; go to the motor disconnect box, turn it off,
perform the continuity and resistance test on the “T” leads,
again; if the readings are good, the problem is in the
wires from the motor controller to the disconnect switch;
- check the three wires by disconnecting all three wires
from switch and twist together; go to controller
and check for ground
with megger, check for continuity between A to C, B to
C, A to C; one or more wires will be open or grounded;
- correct solution is to pull all new wires in from controller
to motor disconnect switch, whatever caused the problem
may have damaged the other wires, also; replace all wires
if problem is on motor side of disconnect switch, open
motor connection box and disconnect motor;
- check motor for resistance to ground with megohmmeter,
if reading is below 500,000 ohms, motor is grounded
and must be replaced;
- test motor windings for ohms between phases with ohmmeter
A to B, B to C, A to C, readings should be within
1 or 2 ohms
of each other; if readings indicate open or a significant
ohmage difference, replace motor;
- if motor test readings are good, test the motor leads
between the disconnect switch and the motor connection box
for continuity
and ground resistance, if readings are not good, replace
wires;
- if all readings are OK, reconnect motor, remove lockout,
and restore to service; the problem could have been
mechanical in nature; an overload on motor caused by the
chain, belt,
bad bearings, faulty gearbox, or power glitch.
Motor Controller
- check motor Full Load Amps (FLA) at motor and check setting
on controller overload (OL) device; most newer OL devices
are adjustable between certain ranges, some older OL devices
use
heaters for a given amperage
- if circuit disconnecting means in controller is a circuit
breaker, it should be sized correctly
- if the disconnecting means is a Motor Circuit Protector
(MCP), the MCP must be correctly sized for the motor it is
protecting
and the MCP has a trip setting unit which has to be
correctly set based on the Full Load Amperage of the motor;
using
a small screwdriver, push in on the screw head of the
device and move
to a multiple of thirteen of the FLA; example: a motor
FLA
of 10 amps would require that the MCP trip device be
set to an instantaneous trip point of 130 amps
- fuses protecting the motor should be the dual element
or current limiting type and based on the motor FLA
Progammable Logic Controllers (PLC)
- check to ensure main power is on( 120 VAC
- check 24V power available
- identify problem area
- check sensor operation in problem area
- check sensor Inputs to PLC
- check on PLC that a change in sensor state causes the
corresponding Input LED on the PLC to go on or off
- identify Output controlled by Input on PLC ladder
diagram
- ensure that Output LED is cycling on/off with Input
- check that Output voltage is correct and cycling
on/off with Input
- locate Output device and ensure that voltage
is reaching device and cycling with Input
- ensure that Output device is working correctly
(solenoid coil, relay coil, contactor
coil, etc.)
- an Input or Output module can be defective
in one area or circuit and work correctly
in all
other
circuits
- if each field circuit is not fuse protected,
the modular internal circuit becomes
a fuse and can
be destroyed
by a field short
circuit or any other overcurrent
condition
- check modular circuit; if bad, module
must be replaced after correcting
field fault
- shut down PLC prior to changing any
module -main power and 24V
power
- locate fault in field circuit by
disconnecting wires at module
and field device, check
between wires for
short circuit and
to ground for short circuit;
replace wire is short circuit found
- check device for ground, short
circuit, mechanical and
electrical operation,
even when problem
found in wires,
always also
check device for another
fault, problem in wires can cause
problem in device or vice versa; if device
defective, replace device
and then check total circuit
before placing
in operation
and after restoring circuit,
check again to ensure circuit
and
module are operating correctly
- check power supply module;
if no output, shut down
power and
replace
supply
module
back plane can go bad,
some of the modules with
power
and others
with
no power,
replace backplane
- sometimes, the PLC can be
reset using the Reset
keyswitch; ensure that
turning the
PLC off
won’t interrupt
other running sub-set
programs, turn keyswitch
to far right, after
15 seconds, turn to
far left wait, then
return to middle
position; this operation
should reset program
and enable a restart
- the PLC program can have
a latch relay with
no reset under
certain
conditions,
the keyswitch
reset may
have no affect
on the latch, try
turning the power to the PLC
off and back on,
this operation may reset the latch and
allow
the program
to be restarted
the PLC is usually
part of a control
circuit
supplied with
120VAC through
a 460V/120V
transformer as
part of a system
with motors, controllers,
safety circuits,
and other controls;
occasionally, cycling
the main
480V power
off/on will be
necessary to try
to reset
all the safety and
control circuits
- possession and use of
an up-to-date ladder
diagram,
elementary
wiring diagram, manufacturer’s manuals & diagrams,
troubleshooting skills, operator’s
knowledge, and time
are all required
to solve issues involved
in maintaining a
modern manufacturing
production line
About the author
Larry Bush finished basic electrical training at a US Navy
school in 1957 and has worked continuously as an electrician,
electrical supervisor, electrical field engineer, maintenance
supervisor, maintenance foreman, maintenance manager, or
plant engineer for 47 years. Mr. Bush reached the rating
of Electrician’s
Mate Second Class, submarine qualified; worked as a Journeyman
Marine Electrician IBEW & MFU, and Journeyman Maintenance
Electrician in IBEW, GBBA, USW, & Teamsters; Electrician
card from US Coast Guard for Merchant Marine; and journeyman
construction electrician (not necessarily in that order).
|