| Optimizing Lube PMs
Drew Troyer, Noria Corporation
Posted 10-25-04
"Ultimately,
human intentionality is the most
powerful evolutionary force on this planet."
-George
Leonard
Grease
a bearing, change the oil, decontaminate a system, change a filter . . . why
do we perform these tasks, commonly called preventive maintenance or PMs and
what drives the frequency with which they are performed? Sadly, few maintenance
managers can truly answer these questions. When selected correctly, PMs are
performed with intention . . . there is a belief that a causal relationship
exists between the performance of the task and some desirable result, such as
improved reliability and/or reduced maintenance cost. Regrettably, PMs are often
selected, scheduled and carried out with little thought regarding this critical
relationship, or ineffective PMs are perpetuated simply because that is the
easiest path. As a result, resources employed to complete PMs are often wasted
(Figure 1).

In my consulting experience,
when a manager or engineer is asked why a lubrication PM is performed at a particular
interval or in a particular way, the answer is usually "I don't know, "the OEM
manual says to do it that way" or the universal "we have always done it that
way." In today's global market, these answers aren't good enough. Today's industry
requires precision reliability and maximized return on net assets (RONA), which
in turn demands precision maintenance, including lubrication. The low cost producer
in a given market segment will not have the luxury to carry out lubrication
PMs in the casual manner in which they been performed in the past. They must
be optimized with respect to cost and benefit.
A number of common mistakes
are made in selecting, scoping and carrying out lubrication PM tasks and intervals.
I have outlined four common "wrongs" with respect to lube PM optimization, which
can, with some effort and guidance, be turned into four "rights."
Wrong Task
Sometimes, the required task is not included in the lube PM program. For example,
routine inspections often don't include all the parameters that they should,
a machine is not on an oil analysis program, but should be or a machine's lubricant
should be periodically decontaminated but it is not. In other cases, lube PMs
are in the system that shouldn't be. For example, scheduled tasks that should
be replaced with condition-based tasks, or tasks that have been piled onto a
machine in response to a failure for which no clear understanding about why
the failure occurred was established.
We want to perform the right
lube PM tasks . . . those that eliminate, or reduce the likelihood of potential
failures. Task selection should be driven by the inductive failure modes, effects
and criticality analysis (FMECA) and deductive failure root cause analysis (RCA).
Where RCA is used to add or eliminate a PM tasks, be sure a clear cause-effect
relationship exists. Confirm that retained tasks do indeed produce the desired
result.
Wrong Interval
Sometimes, the interval between scheduled tasks is too long, which leaves machines
running dry, or operating with degraded or contaminated lubricant. In other
cases, the interval is too short, which can lead to seal damage and a loss of
contaminant exclusion effectiveness, friction and heat generation, leaks, spills
and overflow, and wasted materials and labor.
When defining a lube PM
task interval, start with any available OEM recommendations, but consider the
operating environment and application in the decision. In some cases, OEM manuals
don't spell out lube PM tasks in sufficient detail, or the manuals are grossly
outdated. In these cases it is necessary to calculate lube PM task intervals
using available formulas and so-called "wizards," employ measurements to empirically
verify the validity of the task interval, or use some combination of formulas
and empirical verification. Like task selection, the lube PM task interval should
be driven by FMECA and RCA.
Wrong Design or Technology
We routinely see lube PM tasks that can't be performed due to lack of access.
Either the machine's design physically excludes access to the lube point, accessing
the lube point would create a safety risk for the lube tech or completion of
the task requires the machine to be shutdown or slowed down.
When purchasing a machine,
one may choose to minimize the acquisition cost, or to minimize the life cycle
cost. The life cycle cost is the present value of all costs associated with
asset ownership, including acquisition, operation, maintenance and disposition.
Maintainability (for example, correct lubrication system, accessibility for
relubrication) is often compromised when the acquisition cost minimization-based
purchase process is employed. Consider lubrication maintainability carefully
when purchasing a new piece of equipment.
In other cases, the application
is made tougher (such as extended periods between scheduled outages), the environment
has changed, it was impossible to foresee application and environmental challenges
during the design phase, or technology has changed. In these instances, it is
necessary to modify the machine to optimize the lubrication system, which includes
lube delivery, contamination control, inspections, sampling, etc., to reflect
the true needs of the equipment. Again, the design and/or modification process
should be driven by FMECA and RCA.
Wrong Procedure
Often, the lube PM task and interval are selected properly, and the technology
and design are correct, but the task is not completed properly. This is because
the procedure is nonexistent, wrong, unclear and/or hard to follow, unavailable
or difficult to access, not trained or not enforced. The procedure is the manifestation
of a well-engineered machinery lubrication program. Once lube PM tasks are selected,
the interval is optimized and any design or technology modifications are completed,
it is necessary to create, implement, train and enforce procedures that ensure
that the intended task is completed in a way that delivers the intended result.
The entire lubrication PM
program, once it is optimized, must be periodically revisited to ensure that
it achieves its intended objectives. Technology changes, the application changes,
management's objectives change and the operating environment change; a periodic
review and update of your lube PM program is a must. Think of it as preventive
maintenance for your lube PM program.
The entire idea of optimizing
lubrication PMs may seem daunting. However, it is not in the best interest of
the organization to dedicate such a large portion of the maintenance budget
to a PM program that fails to deliver the desired level reliability and low
cost of ownership. Ben Franklin once said "an ounce of prevention is worth a
pound of cure." His quote summarizes the reasoning behind developing a PM program
in the first place. It seems appropriate to apply this same logic to the design,
deployment and management of the PM program itself.
This discussion is not intended
to serve as a technical foundation from which to reinvent your lubrication PM
program. Rather, it is intended to provoke thought and discussion. Look for
a detailed article, or series of articles, on developing and managing an effective
lubrication PM program in future issues of Machinery Lubrication magazine.
Drew Troyer, "Optimizing Lube PMs". Machinery
Lubrication Magazine. September 2002
This is my viewpoint. As
always, I'm interested in yours. |