Switch In Contract, Maintenance Proves Costly
Ron Moore, The RM Group
Posted 07-22-03
In May 1995, a company we will call ACME North America to
protect its identity, began a focused effort to improve manufacturing
performance at one of its major production facilities. Particular
attention was given to improving plant reliability and its
potential impact on increased uptime and lower maintenance
costs.
ACME North America had a respectable profit on sales, and
revenues stood at several $100 million. The company was taking
prudent action to assure its long-term financial health.
Over the next several months, a number of performance measures
were put into place, and specific actions were taken to improve
maintenance performance. These included measuring uptime and
the causes of lost uptime, as well as implementing certain
maintenance improvement tools such as:
- Maintenance planning and scheduling and routine preventive
maintenance (PM) activities
- Several predictive maintenance technologies
- More proactive efforts, such as root cause failure analysis
and precision alignment and balancing of critical equipment
- Operator PM efforts to improve equipment basic care and
to relieve maintenance of several routine tasks
- Assignment of a manufacturing reliability engineer to facilitate
the implementation of these practices in a comprehensive
manner.
Prior to these efforts, maintaining high uptime had become
increasingly difficult, with uptime typically 70 percent or
higher, but rarely better than 80 percent. Following the implementation
of the reliability program, uptime improved steadily to a peak
of 88 percent.
Maintenance costs trended steadily downward after implementing
reliability practices, going from $980,000 per month to $480,000
per month.
Reactive maintenance dropped from about 70 percent in mid-1995
to about 30 percent in August 1996. The reduction in reactive
maintenance, which typically costs twice that of planned maintenance,
was a result of implementing specific preventive (time based)
maintenance, predictive (condition based) maintenance, and
proactive (root cause based) maintenance practices in an integrated,
comprehensive way. In particular, predictive maintenance was
used to confirm the need for scheduled efforts, to trend the
condition of equipment, to diagnose the root cause of certain
repeated problems, and to balance the need for preventive and
proactive maintenance, making it more optimal.
Financial data were normalized by a fixed constant to maintain
the confidentiality of the actual data.
Consolidating maintenance contractors
In parallel with the reliability program, the company's purchasing
department in the second quarter of 1995 determined that considerable
money could be saved by consolidating contractors on site,
reducing the administrative and management effort associated
with those contractors. It felt this was particularly true
for maintenance and related contractors, such as those involved
with minor capital and construction projects. The decision
was made in June 1996 and the consolidation process began in
September.
Simultaneously, at the corporate level, considerable benchmarking
led management to conclude that maintenance costs were too
high, and that productivity (units of product per employee)
was too low. After considerable debate, and apparently unable
to wait long enough to realize the full benefit of the improvement
process already being established, management decided to cut
the number of employees, with maintenance employees being reduced
by about half.
Uptime dropped immediately to about 66 percent, then rose
gradually to near 86 percent-dropping thereafter for an average
of about 75 percent for the period from September 1996 to June
1997. However, it should be highlighted that the immediate
drop in uptime in September was related to two specific equipment
failure events (a large motor and a heat exchanger), and those
specific events should not be attributed to the consolidation
effort, or to the downsizing effort. As luck would have it,
however, the timing of those failures was very inopportune.
And, nonetheless, the plant has had great difficulty recovering
to levels of performance exhibited prior to the downsizing
and contractor consolidation. Overall, uptime dropped from
about 82 percent to 75 percent following these actions.
In the first quarter of maintenance contractor consolidation,
maintenance costs soared to more than $1,080,000 by December
1996, over twice August and September's levels, and significantly
above costs a year earlier when the reliability improvement
program began.
As of June 1997, maintenance costs were still at $880,000
per month, a comparable level to that of October 1995. In effect,
after nearly two years of effort, maintenance costs had not
improved, and in fact had increased substantially from about
a year earlier.
The level of reactive maintenance had trended downward until
August 1996, even continuing downward into November to some
20 percent. However, as consolidated contractor staffing levels
and work efforts increased, predictive maintenance was essentially
eliminated, giving way to time based or preventive maintenance
because the contractor was apparently not familiar with condition
based maintenance methods for improving maintenance performance.
Coincidentally, reactive levels also began to rise, peaking
in May 1997 at over 40 percent -comparable to levels in early
1996 -and in spite of increased PM. Indeed, some studies indicate
a 10-20 percent probability of introducing defects into equipment
using a preventive maintenance approach alone.
Stores issues and purchase orders for maintenance parts about
doubled from early 1996 levels to some $300,000 per month.
Further, purchase order expenses now represented about $150,000
of the total, or about half. This is believed to reflect the
contractor's not understanding or using the stores system -preferring
the use of purchase orders, stores not having the material
required, or some combination of these factors.
The contractor injury rate was initially five times that
of employee injury rate, but it has improved to three times
the employee rate.
Scheduled maintenance was initially less than 20 percent,
but has risen substantially to near 75 percent, although deteriorating
in recent months to near 65 percent.
All in all, performance has been substantially worse than
expectations by almost any measure -worse than before contractor
consolidation, and no better than 1995 when reliability concepts
were first introduced by the company.
What happened?
There were many factors at work; some were beyond the control
of the contractor. The decision to use the new contractor was
driven by a need to consolidate contractors, as well as a perception
that labor costs for contractors were cheaper than in-house
labor. In fact, costs actually increased following consolidation
of contractors. Some of the factors associated with the performance
shortfall include:
- Contractor experience. The contractor's staff had limited
experience with the equipment they were maintaining. As a
result, a substantial learning curve was necessary to become
familiar with the plant, including its equipment, policies,
procedures, and practices. Further, the contractor had limited
experience with condition monitoring (predictive maintenance)
to help optimize time based maintenance. Thus it relied primarily
on a time based approach to maintenance, which is typically
not optimal in and of itself. This is evidenced by the concurrent
increase in reactive maintenance levels, in spite of a substantial
increase in time based maintenance. Finally, many of the
contractor's staff were taken from the construction ranks,
where different work processes and methods are used, resulting
in a more-difficult transition into an operating plant.
- Displaced contractors. Existing contractors, who were in
effect being eliminated, remained on the job for about three
months after the new firm started. These existing contractor
charges increased substantially during this transition period
prior to their departure. While a transition period may be
prudent, better management may have helped mitigate these
costs.
- Shutdown impact. Just prior to the new contractor's arrival,
the entire plant had been shut down for extensive maintenance
efforts and bringing on line a major new production process.
The start up was difficult and time consuming, leaving few
resources to manage the integration of the new maintenance
contractor. Morale problems were inherent in the concurrent
shift of maintenance functions to the contractor. Confusion
was substantial, and morale and productivity were low.
- Transition process. The process for introducing and integrating
the contractor with the plant's work management practices
was poor. There was little understanding of the work order
process used at the plant, of the planning and scheduling
process, and of the maintenance information software currently
in use. There was insufficient management interface, because
of the shutdown and startup efforts, to allow adequate communication
and management of the integration effort.
- Loss of key management staff. Concurrent with the arrival
of the contractor, two key managers at the plant were transferred,
exacerbating the difficulties in providing overall management
and integration of the contractor.
- Loss of skilled staff. Many, if not most, of the employees
skilled in maintaining plant equipment began to leave just
as the new contractor arrived. Some were laid off; others
went on early retirement. Morale was quite low, and the enthusiasm
for "training" the contractor coming in was essentially nonexistent.
Current situation
At this point it is too late to return to the way things
were. The plant has gone through the pain of bringing in, training,
and integrating a consolidated contractor, whose staff is now
familiar enough with the equipment and work processes to perform
in a reasonably effective manner. However, costs are still
substantially above what they should be for world-class performance,
and indeed are above what they were when the contractor arrived.
Given this, and that almost all operating units will (and
should) continue to use the contractor to support world-class
performance, it is appropriate to meet with the contractor
on a regular basis to improve the relationship and to create
clear expectations.
Path forward
Making the contractor an integral part of the operation is
a necessity, not an option; establishing expectations and measures
associated with world-class performance also is a necessity,
not an option.
The guiding principle behind performance measures is that
the contractor must deliver an effect, not simply supply a
service for a fee. Desired effects include improved equipment
life, higher availability and uptime, lower maintenance costs
per unit of contractor supply (for example, normalized to account
for issues such as assets under their care or total product
produced), and excellent safety performance. In other words,
the contractor will be held to the same high standards as the
balance of the organization, and become a genuine partner in
the plant's success. Some of the measures of effect might include
those in the section "Measures of Performance."
A fresh look will be taken at the plant's operation, and
firm leadership will be exercised, particularly regarding expectations
for contractor performance. Maintenance excellence is not an
option, it is a requirement. To achieve excellence, which is
not simply doing a lot of PM, a balanced maintenance program
will be reestablished including greater application of predictive
and proactive methods. More teamwork between maintenance and
operations also will be required to eliminate losses from the
ideal. Too much is at stake for the success of the business.
Therefore, the plant, in cooperation with the contractor, will
assure the following:
- A strong predictive, or condition based, maintenance program,
including operator input of equipment and process condition,
is re-established.
- Existing PM tactics are reviewed with the intent to optimize
them. Maintenance planning and scheduling will be tempered
with good condition monitoring, and the quality of the maintenance
effort will be validated with a commissioning process.
- Operations personnel will become much more involved in
operational reliability and what they can do to improve performance,
including operator PM as appropriate. Operational excellence
is also a requirement, not an option.
This case study of ACME North America produced a number of
lessons for management, staff, and the work force. They are
summarized in the section "Lessons Learned at ACME North America."
Even in the best of circumstances, major changes to any "system" will
always result in transitory effects -the system will generally
get worse before it gets better. This, too, is a cost which
should be considered by management.
It is hoped this case study provides an order of magnitude
estimate of the cost effects which could occur, and will help
avoid those costs. Perhaps the best policy would be to avoid
the costs in the first place. Simply replacing one set of warm
bodies with another will not necessarily deliver the effect
desired.
The processes which result in improved performance must be
put in place. In this instance, that was being done, but was
interrupted by the introduction of a consolidated contractor
through decisions made at the corporate level. The goal of
consolidating contractors to improve administrative and management
costs would have worked, but it was disrupted by several events
not the least of which was a major downsizing.
(A future article will discuss issues related to effective
use of maintenance contractors.)
|