Work Order Prioritisation
Daryl Mather
Too many organisations neglect the benefits of a clearly defined
prioritisation system. Even when they realise the importance
the focus is invariably at a department or functional level.
I have seen organisations where there are up to three or more
prioritisation systems. None of which are inter-related.
Along with work order classification, failure coding and
integration with business processes, this is one of the key
determinants of a maintenance systems future operation. The
drawbacks of not clearly defining the priorities, or defining
them at a departmental level are many, they may include:
- Wasted maintenance man-hours on tasks of low relative importance
- Critical tasks being lost in the maintenance backlog
- Dissatisfied operations customers
- Lack of faith in the effectiveness of the maintenance delivery
functions
- A disciplined method of prioritisation will eradicate tasks
being done on a whim and allow work to proceed according
to its true effect on the overall operations of the plant.
It will also allow the maintenance delivery function to be
executed in a far more effective manner. For example while
works orders of higher priority will remain those that are
scheduled, to achieve the capacity scheduling limits set
by the organisation, there will develop a pool of lesser
priority tasks that can be attended to in an unscheduled
manner. Giving a base for project type works for various
craft disciplines.
System Guidelines
The system will need to cater to the following requirements
equally and give a universal method of coding all works orders.
- Site wide plant equipment priorities, allowing for better
site wide direction of resources
- Operations requirements
- Improvement projects
Accurate prioritisation covers three distinct decision-making
processes, although one may be preset the others will require
a degree of judgement and lastly discretion in executing work
orders practically.
- Equipment Criticality
- Effect of task or work to be done
- Real world limitations on execution
Original priority of the work orders needs to be set by the
originator of the work order.
This person is the most qualified to answer the questions
of equipment criticality and effects of the task/fault noted.
Listings of major equipment and their criticalities will
assist in decision-making, lower criticality items or areas
will be easier to recognise.
The coding system listed below is an example of how to go
about setting a “future proof” prioritisation system for work
order coding. Although this can appear complex at first, once
the required training, documentation and guidance are in place
it becomes an integrated part of daily business processes.
The following criteria could be used to judge equipment criticality
and effect of the works:
| Equipment Criticality |
Description |
| 1 |
Critical safety protective devices |
| 2 |
Critical to entire plant operation |
| 3 |
Critical to continued production of Main Product |
| 4 |
Ancillary System to main production process |
| 5 |
Critical to continued Production of Secondary Products |
| 6 |
Ancillary System to secondary production process |
| 7 |
Stand - by unit in a critical system |
| 8 |
Stand by unit in a non critical system |
| 9 |
Ancillary Equipment |
| Task Effect |
Description |
| A |
Immediate threat to safety of people. |
| B |
Immediate threat to the safety of the plant |
| C |
Limiting Operations ability to meet primary targets |
| D |
Limiting Operations ability to meet secondary targets |
| E |
Hazardous situation, people or machinery, not immediate |
| F |
Will effect operations after time |
| G |
Improve the efficiency of the production process |
| H |
Restoration of the plant technical integrity |
| I |
General improvement to further operability, safety or
maintainability goals |
The combination of the criticality and effect of the work
can be cross-referenced to give a relative weight of each task
in comparison to all other types of works. The colours represent
the time frames with which these priority tasks can be allowed
to occur.
Although open to debate the timeframes for work for work
orders of varying priorities can generally be grouped into
5 or less. This allows for both criticality and effect of work
and is to be a cross reference for all work order assignment.
|
Effects
of Task |
| A |
B |
C |
D |
E |
F |
G |
H |
I |
| 1 |
1A |
1B |
1C |
1D |
1E |
1F |
1G |
1H |
1I |
| 2 |
2A |
2B |
2C |
2D |
2E |
2F |
2G |
2H |
2I |
| 3 |
3A |
3B |
3C |
3D |
3E |
3F |
3G |
3H |
3I |
| 4 |
4A |
4B |
4C |
4D |
4E |
4F |
4G |
4H |
4I |
| 5 |
5A |
5B |
5C |
5D |
5E |
5F |
5G |
5H |
5I |
| 6 |
6A |
6B |
6C |
6D |
6E |
6F |
6G |
6H |
6I |
| 7 |
7A |
7B |
7C |
7D |
7E |
7F |
7G |
7H |
7I |
| 8 |
8A |
8B |
8C |
8D |
8E |
8F |
8G |
8H |
8I |
| 9 |
9A |
9B |
9C |
9D |
9E |
9F |
9G |
9H |
9I |
| Time Frame |
Color |
User Priority |
| 24 hrs |
|
1 |
| 48 hrs |
|
2 |
| 72 hrs |
|
3 |
| 3 weeks |
|
4 |
| 3+ weeks |
|
5 |
As this is only a tool to reach the timeframes represented
by the coding, the effects or equipment criticality rating
can be changed to represent changes in corporate policy, planning
windows or equipment requirements.
Planner Priority
In executing this work there will always be difficulties.
These are associated with:
- Labour shortages
- Plant availability
- Material lead times
To balance these items against the priorities of the plant
as represented by the originator priorities, the planner requires
a system of coding work orders to determine how they will practically
be completed. The degree of flexibility needs to be built into
the coding system.
This adds a third dimension to the prioritisation process
and allows for the consideration of real world limitations
on workflows. Including rapid changes to overall operations
priority.
Although there are many recommended approaches to prioritisation,
I would recommend this system as one that is suited to organisations
where the maintenance function may cover various plants or
ranges of equipment. As well it can easily be adapted if the
organisation decides to re-structure itself. (As happens frequently)
No matter which approach is used, without it the maintenance
department cannot continually carry out its function with any
degree of certainty. For any further information regarding
prioritising systems, or for information relating to any other
basic aspect of maintenance planning or scheduling please do
not hesitate to contact me directly. |