Backlog Management
Daryl Mather
Few tools are as useful to managing the maintenance workload
and effectiveness as the Maintenance Backlog. In many companies
today management of the maintenance backlog has been neglected.
As a result they are generally drowning in their own data.
A poorly managed system has a dramatic effect on the entire
delivery of maintenance services.
Although the situation may appear random and chaotic, there
are several common symptoms of poor backlog management. From
my observations of various maintenance demanding industries,
these may include:
- Many duplicate works orders. This is one of the
main issues causing waste in this area. Particularly if undiscovered
they can result in wasted resources investigating already
completed tasks. There are also the effects of re-ordering
unrequired materials and additional planning effort.
- Non-standardised free text entries. Affecting
future analysis and continuous improvement. This can also
lead to confusion in planning and execution of works.
- No indication of forward resource requirements. Giving
only best guess indications as to the true manning levels
required.
- Poor coding of work orders (No business rules to guide
these) Affecting the future analysis and continuous
improvement function. This can contribute to important
works being buried among the work order listing.
- Little focus on priorities, many unprioritised work
orders. This results in corrective actions on the
whim either the supervisor, or section manager. As there
is nothing substantial to use as a guide, or give a rating
relevant to other backlog works.
- Many tasks not kept in the backlog system. Maintained
in lists external to the corporate system. Faith in the backlog
system, and the maintenance delivery systems in general,
are eroded.
- Unrequired works passing through the work order
system, resulting in unnecessary expenditure.
As well as all of these issues, an accurately managed backlog
is the precursor to effective planning and scheduling systems,
which is a key driver of labour productivity.
Gaining control of the maintenance backlog is initially a
difficult task. Requiring a great deal of effort and process
development. Keeping it under control is the product of correctly
targeted systems applied in a disciplined manner by skilled
planners, supervisors and all involved in the work order process.
A correctly maintained backlog system will provide many benefits
to the organisation. The system has control over the quality
of tasks to be performed, quality of data used in this execution
and the quality of data returning to the system or files for
future analysis or improvement. Maintenance cannot move past
the reactive stage without a firm control over this area.
Work Order Life Cycles
A clear-cut work order life cycle needs firstly to be developed.
This needs to cover the full life of a works order from its
inception to its later roles in analysis. Points for quality
reviews need to be established for both data integrity control,
as well as suitability for execution.
Once the system for this has been established, the process
needs to be clearly communicated to all involved in it. Particular
emphasis is needed on the role that the individual holds and
any relationships to others in the process.
The following example of a work order life cycle is a process
I have seen used or adapted many times, each with an almost
immediate effect. However this system needs to be developed
with the goals of each specific corporation in mind. Differences
in creation criteria, forward activity forecasting, and standardisation
levels for free text as well as methods for controlling work
orders are common areas of difference.
Creation
As the foundation of all the system, specific focus can assist
greatly here.
Setting of criteria for what constitutes a works order.
Daily reviews by authoriser / planner for conformance to
business standards and rules. Eg Classification, Priority,
clarity of text, sufficiency of detail for further works. This
can best be accomplished by a request system, using the planner
to code and manage the work order details. The request system
does need to contain a strong measure of specific data however.
Integration of the daily work request / work order reports
into the morning operations meetings.
- Review of Breakdown works orders
- Discussion as to other higher priority ones.
Backlog Life
It is advisable to always have at least one weeks planned
works ahead. Although the PM schedules can generally be planned/scheduled
out way in advance there is generally not enough for 100% capacity
scheduling of labour hours for more than three – five weeks
And with weekly scheduling regimes, and opportune windows,
this is a good minimum level.
During this life the work order needs to pass through various
controls and processes:
- Planning
- Resourcing and $cost estimating
- Priority reviews
- Age by priority reviews
- Scheduling of “Planned” works only
- Execution and Data capture processes.
- Execution and planning analysis and exception reporting
- Reliability reporting
All of these are vital steps that need to be explored and
organised to create an efficient system. Planning needs to
be to a certain level of information, parts to be within a
certain period, documentation prepared, the work executed in
a safe and timely fashion and the data needs to be of high
quality for reviewing the system.
By applying controls, accurate processes and of course role-specific
training in these areas the backlog becomes a more efficient
tools for use reducing waste of labour hours, parts resources
and planning time. Other areas of course need to be focused
on but this will provide the base for later improvements. |