Protection of Equipment During Storage,
Standby and Decommissioning
www.machinerylubrication.com
Posted 7-11-05
Maintaining spares and redundant machinery in a prime state,
ready for operation, can be a daunting proposition, particularly
given that most of the planet is covered with a substance
that tends to attack these stored and standby machines. We
call the substance water. It is vital to life, health, happiness
and keeping the wheels turning in the wide world of manufacturing.
Water also has the distinct potential to wreck idle industrial
machines.
Machinery can be idle from intermittent use, stand-by (redundancy),
storage for spare parts, or for temporary decommissioning.
This article looks at practices that protect equipment characterized
as decommissioned, short-term storage or storage of stand-by
capacity.
Asset Preparation for Decommissioning
Preserving or inhibiting corrosion of inactive process machinery
depends on the type of equipment, expected length of inactivity
and the time required to restore the equipment to service.
Petrochemical companies usually develop their standards based
on such criteria. One recent typical mothballing program for
indefinite storage in a northern climate zone was planned
and executed as follows and forms the basis for the author’s
recommendations.
Centrifugal and Rotary Pumps
- Flush pumps and drain casing.
- Neutralize acid or caustic pumps.
- Fresh water flush and air-dry all cooling jackets.
- Fill pump casing with mineral oil containing five percent
rust-preventive concentrate. (Specific products for rust
preventives that can be used as vapor-phase inhibitors for
wet systems include Cortec or similar products available
from companies such as VpCI Technology.)
- Plug cooling water jackets - bearing and stuffing box
- but keep low-point drain valve cracked open slightly.
- Coat space where shaft protrudes through bearing or stuffing
box housings with Product 1 (see Table 1) or similar product
and cover with tape.
- Coat all coupling parts except elastomers with Product
1.
- Coat all exposed machined surfaces with Product 1.
- Fill bearing housing with mineral oil containing five
percent rust-preventive concentrate.
- Pumps do not require rotation.
- Close pump suction and discharge block valves.
Reciprocating Pumps
- Flush and drain pump casing.
- Neutralize if caustic or acid.
- Blind suction and discharge nozzles of pump
- Fill liquid end with mineral oil containing five percent
rust-preventive concentrate. Bar piston over to coat all
surfaces. Allow some space for thermal expansion.
- Fill steam end with mineral oil containing five percent
rust-preventive concentrate. Bar piston to coat all surfaces.
- Close inlet and outlet valves.
- Coat all joints where shaft protrudes from casings with
Product 1. Cover with tape.
- Coat exposed piston rod, shafts and machined parts with
Product 1.
- Fill bearing housing and gearbox with mineral oil containing
five percent rust-preventive concentrate.
- Fill packing lubricator with mineral oil containing five
percent rust-preventive concentrate.
Turbines
- Isolate from steam system.
- Seal shaft openings with silicone rubber caulking (Sealastic®
or equal - black to discourage pilfering) and tape.
- Dry out with air.
- Fill turbine casing with oil containing five percent rust-preventive
concentrate including steam chest. Hold governor valve open
as necessary to ensure chest is full. Vent casing, as required,
to remove trapped air. Fill trip and throttle valve with
oil.
- Install a valved pipe on casing which can serve as filler
pipe for adding oil to fill casing.
- Allow space for thermal expansion of oil in pipe.
- Coat all external machined surfaces, cams, shafts, levers
and valve stems with Product 1.
- Coat space between case and protrusion of shaft with
Product 1. Cover space with tape.
- Fill bearing housing with oil.
- Coat casing bolts with Product 1.
Large Fans
- Coat coupling and all external machined surfaces with
Product 1.
- Spray Product 2 on fan wheel.
- Crack open casing low-point drain valve.
Gearboxes
- Fill gearbox and piping with oil containing five percent
Product 1.
- Plug all vents. Allow space for thermal expansion.
- Install a valved pipe on casing which can serve as filler
pipe for adding oil to fill casing.
Large Motors
- Blank oil return line.
- Seal shaft openings with silicone rubber caulking and
tape.
- Fill bearing housing with oil containing five percent
rust-preventive concentrate.
- Install a valved standpipe such that the inlet is higher
than the bearing housing.
- Coat all exposed machined parts with Product 1.
- Do not rotate motor.
Centrifugal Process Compressors
- Purge compressor casing of hydrocarbons.
- Flush internals with solvent to remove heavy polymers.
- Pressurize casing with nitrogen.
- Mix five percent rust-preventive concentrate to existing
lube and seal oil. Circulate oil through the entire system
for one hour.
- Blank oil return header.
- Seal shaft openings with silicone rubber caulking and
tape.
- Fill bearing housing with oil containing five percent
rust-preventive concentrate by running turbine-driven pump
at reduced speed.
- Fill oil console with mineral oil containing five percent
rust-preventive concentrate.
- Fill compressor with nitrogen when it is at ambient temperature.
Turn off all heat tracers.
- Coat all exposed machined parts, including couplings,
with Product 1.
Lube and Seal Oil System
- Add five percent rust-preventive concentrate to lube and
seal oil.
- Circulate oil throughout piping system. Open and close
control and bypass valves so that oil will reach and coat
all piping and components. Circulate for one hour. Vent
trapped air from all components and high points.
- Block in filters and coolers. Fill with oil containing
five percent rust-preventive concentrate but allow small
space for thermal expansion. The water side of coolers should
be drained and air-dried. Plug all vents. Lock drain connections
in slightly open position.
- Fill reservoir with oil containing five percent rust-preventive
concentrate. Blind or plug all connections to tank including
vent stack.
- Coat exposed shaft surfaces and couplings of oil pumps
with Product 1.
Reciprocating Compressors
- Purge compressor cylinders of hydrocarbons.
- Blank compressor suction and discharge.
- Fill crankcase, cooling water jacket and valves with
oil containing five percent rust-preventive concentrate.
Install a valved standpipe. Allow space for thermal expansion.
- Coat all exposed machined parts with Product 1.
- Top-up oil level in the cooling water jacket.
Short-term Equipment Storage Strategy
The probability of equipment failure is high following commissioning
of equipment, whether for initial operation or following rebuild.
Machines can often sit at a new industrial site for months
while the arduous process of site construction creeps along.
Unless the buyer clearly specifies storage measures in the
contract, it is likely that the machine would be shipped without
provision for storage. Onsite storage preparation for the
three to 12 months at a construction site is usually termed
a preventive maintenance (PM) program. Storage protection
plans would look like the following, again in a northern,
dry climate:
Rotation
Rotate all motors, turbines, compressors, pumps (excluding
deep well pumps with rubber bushings), fin fans, blowers,
aerators, mixers and feeders every two weeks.
Visual Inspection
When rotating exposed machined surfaces, check shafts and
couplings to see that a protective coating has been applied
and has not been removed. Reapply if needed.
Check all lubricating lines to see if any tubing, piping,
tank or sump covers have been removed. Retape ends and cover.
If flanges are open on machinery, notify pipe fitter general
foreman or other designated personnel.
Inspect the interior of lube oil consoles on a six-week schedule.
Check to see if the reservoir is clean and rust- and condensate-free.
Clean and dry if needed, then fog with rust-preventive concentrate.
Draining of Condensate
Drain condensation from all bearing housings, sumps and oil
reservoirs on a once-per-month schedule. If an excessive amount
of condensation is found, recheck once a week, or at two-week
intervals depending on condensate present.
Bearings
Fill all bearing housings that are oil-lubricated but not
force-fed with rust-preventive concentrate, bringing the oil
level up to the bottom of the shaft. For force-fed bearings,
the upper bearing cap and bearing must be removed. A coat
of heavy, inhibited oil can be applied to the journal and
bearing surfaces. This should be reapplied as needed.
Turbines
Spot-check turbines by removing the upper half of the turbine
case and visually inspect. Plan to open a sampling of these
turbines, selecting from the first preserved and those in
the worst condition. This should be done on a three-month
schedule. Other turbines may be inspected by the manufacturer’s
field service engineer on his monthly visits. Small, general-purpose
turbines should be fogged with rust-preventive concentrate
through the opening in the top case as the rotor is being
rotated. This should be done on a three-month schedule.
Compressors
Manufacturers’ representatives should inspect the compressors
during monthly visits. Preservatives needed can be applied
under their supervision. Fog centrifugal process compressors,
and consider placing desiccant bags in these machines. Inspect
these compressors on a two-month schedule. Inspect high-speed
air compressors on a three-month schedule. Inspect and fog
axial compressors on a three-month schedule.
Pumps
Open reciprocating pumps and inspect on a two-month schedule.
Fog centrifugal and in-line pumps with rust-preventive concentrate.
Volute cases need not be filled unless it is anticipated that
they will remain out of service for longer than one year.
Electric Motors
Electric motors with greased bearings need not be lubricated.
If received with a grease fitting it should be removed and
plugged or capped. For other lubrication type bearings, see
bearings section of this article.
Speed Reducing or Increasing Gears
Fog the interior of the housing with rust-preventive concentrate.
Coat tooth contact points with an inhibited grease or heavy,
tacky oil. Remove inspection plates on gears and visually
inspect interiors on a three-month schedule.
Blowers
Inspect blowers for rust on a three-month schedule.
Mixers
Fill mixers with rust-preventive concentrate.
Fin Fans
Drive belts should stay on. Run several minutes at least every
two weeks or whenever snow load dictates.
Miscellaneous Equipment
Lubricate miscellaneous equipment as applicable and rotate
on a two-week schedule.
Other Considerations
In a warm, high-precipitation climate it is wise to look for
alternate solutions to the problem of field storage during
construction and prior to start-up. If oil-mist lubrication
is not already part of the original design, it should be seriously
considered as in many cases it provides the best protection
against contaminant ingression.

Figure 1. Temporary Oil Mist Lines and Generator Used
to Protect Equipment Prior to Installation
Figure 1 shows temporary field tubing that supplies oil mist
to the bearing points of a turbine drive pump row.

Figure 2. Open Storage Yard with Oil Mist Tubing
Protecting Pump and Motor Bearings
Figure 2 shows a similar installation, feeding oil mist to
pump and motor bearings.

Figure 3. 15,000-hp Electric Motor Stored with Oil Mist
Preservation on the Bearing Housings
Figure 3 illustrates construction site storage oil mist supply
lines that run to a vertical mechanical drive turbine as well
as to a large feed pump motor.
Storage for Stand-by Capacity
The third and last case of machinery storage protection arises
when standby capability of inactive equipment is desired.
Reference 1 describes such a case. It appears as though there
are no limits to the ingenuity displayed by operators, as
long as a “do nothing and take your chances” stance
is not taken. In addition, best practice dictates that all
preventive maintenance be logged by item number in the maintenance
log.
While the case of extended standby protection does not seem
to present a problem for process pumps and other general-purpose
equipment, especially where oil-mist lubrication is installed
and operating, it might well be a challenge to operators of
steam and gas turbines as well as reciprocating engines and
compressors. One company has had excellent success with a
program it developed in-house for standby storage of critical
machinery, particularly gas turbines. Following is one manufacturer’s
recommendations for the standby protection of gas engines
or gas engine-driven compressors:
Drain the water jackets and then circulate the proper compound
(see Table 1) through the jackets making sure that all surfaces
in the jacket are reached. Drain the system and plug all openings.
Lubrication Systems of Engines
For engine lubrication systems, the following procedure is
recommended:
- Drain the lubricating oil system, including filters, coolers,
governors and mechanical lubricators. Flush the complete
system with standard petroleum solvent that will take the
oil off the surfaces. Use an external pump to force solvent
through the system. Spray the interior of the crankcase
thoroughly, then drain.
- Refill with Product 4 to the minimum level, just enough
to ensure pump suction at all times, in each case. Crank
the mechanical lubricator by hand until all lines are purged.
Where compressors are used, be sure to flood the compressor
rod packing.
- Using air pressure or any other convenient means, turn
the engine at sufficient speed and for a sufficient length
of time to thoroughly circulate the compound through the
engine.
- Stop and drain the engine sump, filters, coolers, governor,
lubricators, etc. Plug all openings.
- Remove the spark plugs or gas injection valves and spray
with Product 2 inside the cylinders, covering all surfaces.
At the same time, rotate the engine by hand so that each
piston is on bottom dead center when that particular cylinder
is being sprayed.
- After this operation the engine should not be turned
or barred over until it is ready to be placed in service.
Tag the engine in several prominent places with warning
tags.
- Where compressors are involved, including scavenging
air compressors, remove the valves and spray inside the
cylinder to cover all surfaces. Dip the compressor valves
in Product 1 and drain off the excess. Reassemble valves
in place.
Reference
Bloch, H. and Shamim, A. 1995. Oil Mist Lubrication: Practical
Applications. Lilburn, G: Fairmont Press.
|