Eliminating Conveyor Concerns
Flexible
Steel Lacing Company
It's hard to imagine belt conveyors anywhere playing a more
important role than at South Africa's Kendal Power Station.
Here, the world's largest black-coal-fired electrical generating
complex converts up to 1.4 million tons a month into more than
4100 megawatts, enough to supply three cities the size of nearby
greater Johannesburg. Coal streams in on twin overland conveyor
lines directly from Khutala mine, in the Bombardie Cologne
coalfield about 5.75 beltline km (3.6 mi) to the south. At
the other end of the powerplant, a monthly ashflow of up to
540,000 tons streams out on another twin conveyor system, heading
for a landfill site about 1.5km (.9 mi) away.
While downtime is an unwelcome visitor in any conveyor system,
here it threatened to be quite costly by either choking off
electrical output or demanding emergency handling of ash that
keeps coming regardless of whether a conveyor is there to take
it away. Perhaps the biggest problem plaguing Kendal's conveyors
at both ends -- frequent shutdowns due to belt slippage --
was virtually eliminated when plant engineers discovered the
magic of ceramic-tile drive pulley lagging.
Eleven years in construction, Kendal was officially opened
in October, 1994, as a state-of-the-art facility and largest
of 24 power stations owned by government-controlled Eskom,
which together produce 95% of South Africa's electrical power
and more than half of all power generated throughout the continent.
Aside from its impressive size and output, Kendal Power Station
also captured the attention of the electrical power industry
as the world's largest producer to use indirect dry cooling.
This technology was pioneered by Eskom to maximize conservation
of water, which already was in limited supply across the Mpumalanga
Province.
Rising abruptly from relatively flat savanna, where herds
of zebra and springbok pay it little attention, Kendal Station
carves a striking skyline with a lineup of six rectangular
boiler houses around 100m (328') tall, flanked by six venturi-type
cooling towers, three at each end of the boilerhouse row. These
towers rank as the world's largest, measuring 165m (541') high
and the same across their base diameter. Commanding the center
of all this are two chimneys reaching heights of 275m (902').
Almost hidden amidst these giants is Kendal's 526m (1,726')-long
turbine hall, where the boiler steam does its work.
Coal Concerns
Nearby to the south lies the plant's Coal Stockyard (CSY),
a 1,200 x 1,000m (3,937 x 3,280') rectangle designed to hold
up to 3.25 million tons. Coal crushed to -38mm (1?") at the
mine comes to the CSY on two parallel overland conveyor lines,
each an end-to-end series of four belts. Both coal streams
pass through the central area of the CSY on two parallel conveyor
lines spread 150m (492') apart. During normal plant operation,
the coal usually continues across the CSY on its way to the
powerplant.
At various times, some of the coal is diverted by two mobile
bucketwheel stacker/reclaimers, which roam the central CSY
belts maintaining "live" piles between the two beltlines. Six
live piles -- three for each machine -- together total about
250,000 tons. These piles are routinely reclaimed in rotation,
each one usually within a week, to feed the powerplant during
early morning or weekend hours when the mine is not coaling.
Two larger areas outside the beltlines -- totaling roughly
80% of the CSY footprint -- each hold "seasonal" piles of 1.5
million tons. There, the coal is compacted to prevent fires,
monitored by infra-red thermographics, and held in reserve
for emergencies.
Upon leaving the CSY, the two conveyor lines regroup and
continue side-by-side along another series of three belts each,
leading into a warren of 25 conveyors called the Terrace System.
Here the coal stream is split up and distributed to thirty
1,000-ton bunkers -- five serving each boiler -- maintaining
an immediate supply that can support eight hours of electrical
generation at full load. Each bunker feeds a dedicated pulverizing
mill, which reduces the coal to powder for injection into the
burners.
Khutala's coal is bituminous, with sulphur content of <1%,
carbon content of 41%, and ash content of 33%. After burning,
99.99% of the resultant fly ash is recaptured by electrostatic
precipitators aided by sulphur trioxide (SO3) injection. The
ash is processed to minimize dusting, then reunited with the
coarse ash that dropped out below the boilers, creating a combined
waste stream of up to 18,000 tons per day. This stream moves
out to the ash dump on two conveyor lines each comprising four
long belts and nine short ones. Its destination is a pair of
ash stacker cranes that creep around on tank-like continuous
treads to spread their deposits. Ultimately, the fully filled
areas they leave behind are covered with topsoil and regrassed.
In total, from mine to landfill, Kendal Power Station depends
on 61 individual belts ranging from 22 to 2,035m (72 to 6,676')
long, center to center, and 1,250 to 2,100mm (49-83") wide,
carrying up to 4,100 tph at speeds from 0.75 to 4.9m (2?-16')
per second.
Avoiding Slippage Shutdowns
According to Coal Plant Senior Engineer Dennis Child, both
coal and ash ends of the system have long suffered the problems
of belt shutdowns or damage due to pulley slippage. "We had
slippage incidents in the CSY at least four times a week during
the rainy season," he recalls, noting that downpours here can
drop 50mm (2") in half an hour. "Between rains, slippage was
fairly normal in early morning when the dew is heavy and we're
reclaiming wet coal off the stockpile. But even in normal dry
weather, we'd be stopped by load-related slippage perhaps six
times a month. In worst cases, we've had rubber-lagged pulleys
chew the bottom cover off the belt down to the cords. We've
had to replace large sections of belt due to such damage --
in one period as much as 40 metres (131') -- at costs that
range from R800 to R1,400 per metre. Often the pulley lagging
needed replacement as well."
While only one belt line from the mine through the CSY can
sustain the powerplant's needs, he points out, one line alone
cannot bring in enough surplus to also replenish the live piles
on schedule. In addition, having one conveyor line down along
that part of the system sets mine production back irreplaceably,
because storage capacity at the mine is minimal.
"In the Terrace," he notes, "one beltline can easily move
enough coal to satisfy all six boilers. However, slippage problems
once stopped both initial incline conveyors -- the two that
bring incoming coal up to the three Terrace Bins to begin distribution.
When the Terrace is unable to supply enough coal, power production
could be affected. If that were to result in shutting down
any boilers, the loss of generating revenue plus the fuel-oil
cost to restart the boilers could run into the millions (Rand)."
Capacity Increase Raises Tensions
Slippage problems threatened to become worse when, in 1998,
work began on a plan to increase the coal plant's design capacity
by about 15% to 15.2 million tons per year. A design review
showed that this would require an approximate 50% speedup in
the first three belts along both overland lines from the mine
to the CSY. This in turn called for greater belt tension to
provide the higher pulley traction needed to pull the belt
load faster. Tension mass in the gravity take-ups would be
increased by at least 45%. Subsequent belts in the coal stream
were wide enough to accept greater loads without any increase
in speed...but they still would need their tensions increased
to accommodate heavier loading.
Kendal engineers then discovered that the take-up towers
used on four belts in the coal stream would not be strong enough
to accept the added weight needed to increase belt tension,
and would have to be rebuilt. Tower take-ups originally were
installed as a design solution to space constraints, Child
explains, and no alternative design was considered practical
here.
Noting the results of ceramic pulley lagging tried at one
of Eskom's other power stations earlier, they suspected that
adding ceramic lagging might achieve the needed increase in
pulley traction without requiring more tension weight.
"We investigated several options," Child recalls, "including
ceramic tiles bonded directly to the drum and ceramic-epoxy
paste applied directly to the drum, but considered these a
bit risky for our application. With the levels of belt tension
common here, we feared that the rigidity of direct-bonded tiles
might damage the belt, and that drum deflection would dislodge
the tiles. An added concern with the paste alternative was
vibration at high speeds, as we felt it would be very difficult
to assure that the paste layer would be truly concentric to
the drum surface. This brought us to conclude that ceramic
tile set in rubber backing would serve our needs best, as its
resilience would withstand drum deflection and avoid belt damage,
while its consistent thickness would prevent eccentric vibrations."
Ceramic Lagging Solves Problem
With that conclusion," he continues, "we set up a test on
a pair of relatively short-cycle conveyor segments we call
CS2A and B." As the first conveyors to start coal moving toward
the Terrace from the CSY, he notes, these are 1,800mm (71")
wide belts, 130m (426') long c-to-c, designed to move 2,665
tph at 2.5m (8.2') per sec. in support of the capacity upgrade. "We
were surprised to see that ceramic lagging allowed us to reduce
the tension mass by 46% and still eliminate slippage trips," he
reports.
Through November of 1998, ceramic lagging was added to eight
more conveyors leading up to and out of the CSY, including
those involved in the speed upgrade, allowing tension mass
reductions ranging from 16% to 73% while virtually ending trips
due to slippage.
By that time, one particularly troublesome conveyor in the
Ash Plant was singled out to try ceramic lagging as well. In
the Ash Plant, Childs explains, belts were fewer but problems
were worse. In contrast to the Coal Plant belts, most of which
are cladded for protection from the elements, Ash Plant belts
are mostly exposed to the environment. With trips averaging
about 70 per month, largely due to rain-induced slippage, belt
availability was down around 65%.
When an ash belt goes down, ash starts piling up at a rate
of about 1,000 tph. "At one point," Child says, "we were paying
outside contractors to truck about 30,000 tons per month to
the landfill at the rate of R6/ton. It became so routine that
we set up an emergency ash dump with a special conveyor to
reload the dumped ash back onto the overland conveyor, using
a front-end loader to clean up the dump at R300/hour...but
even that could cost R150,000 per month."
The conveyor targeted for ceramic lagging was an extendible
unit that alone was largely responsible for the plant's low
availability. This unit transfers ash from an overland conveyor
across 100 to 180m (328-590') to a "shiftable" conveyor that
feeds one of the mobile landfill stackers. "We had endless
problems with this conveyor tripping for various reasons," Child
recalls. "To reduce slippage, maintenance crews tried using
the extendible electric tensioning winch to increase belt tension,
ultimately by about 70%. The rubber drive pulley lagging burnt
to the cover of the belt, winding it up to about three times
the normal diameter of the pulley and snapping the belt."
Spreadsheet Comparison Revealing
From the preceding months of experience with ceramic lagging
in the Coal Plant, Child had developed a detailed spreadsheet
comparing three designs of ceramic-tile-in-rubber lagging.
While they were very much alike in many ways, they differed
in a few criteria that he considered important for future specification.
Most notably, these were % of pulley circumference tiled, adhesive
strength in three key areas and "safe edge" distance.
The first criterion primarily reflects whether the tiles
are in single or double rows, and the spacing between rows,
as tile dimensions are quite similar if not identical. "Among
the three designs, these differences can result in tile coverage
varying from around 65% to more than 80% of pulley circumference," he
explains. "When I specify lagging, I convert the number of
rows around the circumference of the pulley into Rand value.
I also consider the percent coverage of ceramic around the
circumference, because it's the ceramics we are paying for
rather than the rubber backing."
Adhesive strength was measured in terms of pullout force
required, by an independent testing agency. Tile-to-rubber
strength, arguably the most important, ranges from 12N/mm to
18N/mm across the three designs. Rubber-to-metal (pulley surface)
ranges from 11N/mm to 15N/mm, and rubber-to-rubber from 6N/mm
to 8.5N/mm. Rubber-to-rubber strength -- the bond between adjacent
strips of lagging -- is important for barring contamination
through those seams.
"Safe edge" distance is Kendal's term for the distance between
the outer edge of the tile rows and the outer edge of the rubber
backing, which was found to vary from zero to 100mm (3.9") "In
our application," Childs says, "we found at least 50mm (2")
of safe edge desirable because less to none invites trouble
when rigging a pulley, either damaging the sling or breaking
tiles. Besides that, belts rarely extend out to the full width
of the pulley, so any tile in that area is wasted cost."
Finding the Best Value
"Considering the criteria developed in our comparison," he
continues, "we realized that while the ceramic lagging used
in our initial installations was of a lower cost, it was not
our best value, so for the Ash Plant problem we specified Flexco's
Flex-Lag?, which had come out at the top of our comparisons."
Flex-Lag covers the drive pulley faces with 20mm (¾") square
tiles made of high-grade alumina ceramic, molded into flame-resistant
rubber backing, which is bonded to the drum in strips. Each
tile is embossed with 13 small raised "buttons", which embed
into the belt's bottom cover to boost traction. Shallow enough
to avoid damaging the bottom cover, they counteract the decline
of traction that often results as a belt's bottom cover becomes
harder and slicker with age. Flex-Lag ceramic provides 2? times
the traction of grooved rubber lagging under wet/muddy conditions
and 1?-2 times the traction when the system is dry. The combined
thickness of ceramic tiles and rubber backing is less than
12mm (1/2"), but with their characteristic high resistance
to wear, ceramic tiles far outlast standard rubber lagging.
"After installing Flex-Lag in the Ash Plant extendible," Child
says, "we were able to relax that belt's tension from its original
44kN down to an almost unbelievable 8kN. While that belt still
can trip on things like belt skew, overloads, DC failures and
undervoltages, pulley slippage has ceased to be a problem,
so we've reduced trips there by more than half."
From then through June, 2000, as budgets permitted, Flex-Lag
was added to 12 more Ash Plant belt pulleys -- four of which
are on belts with tower take-ups. In that year's second half,
another 14 drives were Flex-Lagged on the coal side, including
those on six 13° incline belts in the Terrace System, where
Child generally was able to remove a ton of tension weight
across the lot. During early 2002, Flex-Lag was added to drive
pulleys on the intermediate and boom belts of both stacker/reclaimers.
Long-Term Savings Projected
Originally, Child continues, all of Kendal's drive pulleys
were installed with diamond-pattern rubber lagging. Because
rubber drive lagging typically lasted only 8 to 10 months in
the Coal Plant, but had much longer life in the Ash Plant,
about 95% of re-lagging activity was focused on coal belts.
To evaluate the potential payback of converting from rubber
to ceramic in both plants, Child charted 40-year cost projections
for both types of lagging on the Coal Plant's longest overland
belt (with tandem drive) and on the Ash Plant extendible. "Although
the cost of new rubber lagging is only about 10% of ceramic
cost," he reports, "the significantly longer service life of
ceramic soon projects a savings on the coal belt, with the
cumulative cost of rubber lagging ending up about 2.5 times
greater than ceramic 40 years out. On the ash belt projection,
where rubber lagging lasts longer, the lower cost of rubber
takes about 9 years to catch up with ceramic, but then continues
to climb to a 55% premium over ceramic by the end of the projection.
The benefit over time is pretty obvious, and the fact that
we don't have to re-lag Coal Plant pulleys every 8 to 10 months
is a bonus."
"Although we built our projections assuming replacement of
ceramic lagging at certain intervals," he admits, "we don't
actually know how long it will last because none of our ceramic-
lagged pulleys have had a failure yet. Considering how little
wear is evident, I'm wondering whether we'll ever have to replace
it."
"I also expect that lower belt tensions resulting from the
ceramic lagging will give us substantial savings over time
among other critical conveyor components such as gearboxes,
couplings and bearings. We initially projected pulley life
around 20 years, but with ceramic lagging and 50% lower belt
tension, I feel we could increase that by another 10 years." |